Quarterly Progress Report Q4 2025
Published: January 15, 2026 · 69 pages
The Quarterly Progress Report Q4 2025 provides a comprehensive overview of project implementation during October–December 2025.
Key Highlights
- Physical progress: 6.0% (against 13.0% elapsed time)
- School site assessments: 245 schools assessed
- Fast-track pilot: Program initiated at 25 schools
- Contract awards: $901,264 across 13 contracts
- Disbursement: $1,163,900 (1.45%)
The report also covers the development of CPD materials for STEM teachers and progress on procurement planning for civil works and goods.